Thursday, August 25, 2011

Job of the Week 8/26/11

Greg and Kim's house in Fort Mill, SC


Job duration: 15 weeks


Highlights of the job:
Fireplace
Grill island (outdoor kitchen)
Large pool deck area
Deck modification
Swim up bar in pool with bar stools in the water!
2 tanning ledges  pool
2 color PebbleSheen interior pool finish (to look like beach sand!)
                                                                                       
Plants
Low voltage lighting
Zeon Zoysia sod
Extensive grading
Extensive drainage work


Job challenges:
Power line relocation
Lot setback and easement lines challenged us to make all the items fit and flow right
Challenging access to site
Challenging slope needed large amounts of soil (over 300 tons of soil!)
Septic tank and leach field we have to design and work around
Existing elevations to work with (basement door, driveway steps, garage back door, right side of house) all had to come together in the end to have the perfect fit and finish.  We did it!!


Check out the before and after photos!  Let us know what you think!!


Message from Greg and Kim:
"We have lived in Fort Mill for over 5 years having relocated back to the area from Texas. We have 4 active children. We have been considering a pool since we moved in because we had one in our previous residence and our current community does not offer this amenity. Because of our active family lifestyle we wanted not only a pool but multiple outdoor entertaining spaces for the adults, teens and tweens. We settled on Overstream after receiving proposals from multiple pool and landscaping companies. Their ability to provide a “one stop shop” and competitive pricing sealed the deal. While we are just starting to enjoy the space we are very pleased with how everything has turned out. Thanks Overstream for making our dreams a reality!"